*Outage Update as of 2/21/2021 at 7:20pm

 

Substation Feeder Description Total Out Now Field Notes
Ben Hur 2413 Thelma/Lake Mexia 1  
Butler 2401 Lanely/Buffalo 5 stringing wire, clearing ROW
Farrar 2411 Farrar/Personville 30 need climbers and track digger
Farrar 2412 TX Westmoreland/Jewett 20 stringing wire
Franklin 2401 Easterly 2 line construction, clearing ROW
Franklin 2402 Owensville 1 line construction, need tracks
Franklin 2404 Shiloh 3  
Freestone 1201 Donie 3 clearing ROW
Freestone 1204 Dew 89 line construction
Groesbeck 1201 Groesbeck/Ft. Parker 1  
Groesbeck 1202 Box Church 5 line construction
Groesbeck 1203 Personville/Lost Prairie 3  
Groesbeck 1204 Shiloh 1  
Hilltop Lakes 1203 Marquez/Bowling 188  
Jewett 1216 Concord 33 stringing wire
Kosse 1202 Kosse/White Rock/Thornton 10 line construction, clearing ROW
Oletha 2401 Lake HQ/Seale 9  
Oletha 2402 XTO/BOA Plant 13  
Petteway 2401 Bremond 29 line construction, clearing ROW
Petteway 2402 Bald Prairie 6 line construction, clearing ROW

 

 

 

 

 

 